Dovers Green School

Project Brief

So, imagine the situation: the summer mad-rush in its final throes and a builder waiting on site for his ventilation contractor to turn up and install the full system solution. No answers to his calls or his emails and then an email arrives on the installation day saying they had stopped production and would not be able to fulfil the order!! Panic calls to all and sundry without success…

Until, one of Corsair’s longest-standing distributors got the call and in turn made the call to Corsair.

 

Corsair Products

 

school ventilation system vortex ventilation system

 

Project Time-line

  • Call on Friday afternoon
  • Site visit Monday
  • Drawings and calcs Wednesday
  • Order Friday/Approvals 3 days later!
  • On-site and Complete: 3 weeks after 1st call

 

To discuss a similar project, contact Corsair Engineering today.